How Much Concrete for a 30x40 Slab

Length × width × thickness ÷ 12: a 30x40 slab 4 in thick is 400 cu ft, 14.81 cu yd, so order 16.5 cu yd.

Units

Slab

Shape
Length
ft
in
Width
ft
in
in

Typical: walks 4 in (10 cm), patios 4 to 6 in (10 to 15 cm), driveways 4 to 8 in (10 to 20 cm).

%

NRMCA suggests ordering 4% to 10% over the plan volume for spillage, uneven ground and form bulge.

Yields from the Quikrete and Sakrete data sheets.

cu yd

NRMCA: mixer trucks carry 8 to 12 cu yd.

Price per
$

Optional. Your store's or supplier's price.

Enter every dimension above zero for each section. A post must be narrower than its hole, and a hole deeper than its gravel base.

A 30x40 slab poured 4 inches thick needs 14.81 cubic yards of concrete (400 cubic feet: 40 ft × 30 ft × 4 in ÷ 12). With 10 percent extra you order 16.5 cubic yards of ready-mix, or buy 734 bags of 80 lb mix and mix it yourself.

A 30x40 slab is 1,200 square feet: a three-car garage, a large workshop or a small barn floor. Trucks, a pump and a finishing crew all matter at this size.

How much concrete for a 30x40 slab, by thickness

Volume is the area times the thickness in feet. The 30x40 slab covers 1200 sq ft. Ordered volumes include 10 percent extra for uneven sub-base and spillage, the middle of the 4 to 10 percent NRMCA range, and ready-mix is sold in quarter yards.

BuildConcrete, netOrder with 10% extraTrucksWeight
4 in, plain14.81 cu yd (400 cu ft)16.5 cu yd261,600 lb
4 in, wire mesh14.81 cu yd (400 cu ft)16.5 cu yd261,600 lb
6 in, rebar22.22 cu yd (600 cu ft)24.5 cu yd392,400 lb

The weight uses 140 lb per cubic foot, Quikrete's figure for the mix. A 6 inch slab is half again the concrete of a 4 inch one for the same footprint, which is worth spending on where a car or a hot tub will sit and not on a walkway.

How many bags of concrete for a 30x40 slab

Bag counts come from the yields on the manufacturers' data sheets: an 80 lb bag makes 0.60 cu ft, 60 lb 0.45, 50 lb 0.375 and 40 lb 0.30. They include the 10 percent allowance.

Bag size4 in slab6 in slab
80 lb734 bags1100 bags
60 lb978 bags1467 bags
50 lb1174 bags1760 bags
40 lb1467 bags2200 bags

734 bags of 80 lb is 29.4 tons of bagged mix to move and mix by hand, and a slab has to be poured before the first batch stiffens. Ready-mix is the practical route at this size. The concrete bag calculator converts any bag size and brand.

30x40 slab cost, three builds

Installed prices at US averages: ready-mix $110 to $150 per cu yd, delivery, fuel and a short-load fee below a full truck, placing and finishing $2 to $3 per sq ft (HomeAdvisor, June 2026), wire mesh $0.83 to $0.98 per sq ft (homewyse, September 2026) and rebar $2 to $3 per sq ft (This Old House, March 2026).

BuildMaterials onlyInstalled rangeTypical per sq ftCrew days
4 in, plain$2,250 to $3,100$4,650 to $6,700 (typical $5,700)$52.5
4 in, wire mesh$3,200 to $4,250$5,600 to $7,900 (typical $6,700)$62.5
6 in, rebar$5,500 to $7,900$7,900 to $11,500 (typical $9,700)$82.5

A 16.5 cu yd order is well below the 8 to 12 yards a truck carries, so the estimate includes a short-load fee of about $330 ($260 to $390). Splitting a truck with a neighbor who is also pouring avoids it. The heavy build adds 109 bars of 20 ft No. 4 rebar in an 18 in grid, about 1,456 lb with laps and 10 percent spare; the rebar calculator lays out the grid.

Joints, thickness and permit

The 2024 IRC sets 3½ in as the minimum for a slab on ground (R506.1) over 4 in of granular base with a vapor retarder under floors. NRMCA advises control joints no farther apart than 24 times the thickness: 8 ft for a 4 in slab, 12 ft for a 6 in slab. On a 30x40 slab that means 4 joints each way at 4 in thick. Under IRC 2024 R105.2, sidewalks and driveways need no permit, and a free-standing patio slab is usually treated the same way. A slab that carries a building, such as a 30x40 garage or shed floor, is part of that building's permit.

Forming, placing and finishing is about 2.5 days for a two-person crew. Concrete reaches 2,500 psi at 7 days and 4,000 psi at 28 days (Quikrete data sheet), so keep vehicles off for the first week.

30x40 slab compared with other sizes

A 24x24 slab saves 7.7 cu yd less, $2,700 less installed.

Next steps for a 30x40 slab