How Much Concrete for a 12x12 Slab

Length × width × thickness ÷ 12: a 12x12 slab 4 in thick is 48 cu ft, 1.78 cu yd, so order 2 cu yd.

Units

Slab

Shape
Length
ft
in
Width
ft
in
in

Typical: walks 4 in (10 cm), patios 4 to 6 in (10 to 15 cm), driveways 4 to 8 in (10 to 20 cm).

%

NRMCA suggests ordering 4% to 10% over the plan volume for spillage, uneven ground and form bulge.

Yields from the Quikrete and Sakrete data sheets.

cu yd

NRMCA: mixer trucks carry 8 to 12 cu yd.

Price per
$

Optional. Your store's or supplier's price.

Enter every dimension above zero for each section. A post must be narrower than its hole, and a hole deeper than its gravel base.

A 12x12 slab poured 4 inches thick needs 1.78 cubic yards of concrete (48 cubic feet: 12 ft × 12 ft × 4 in ÷ 12). With 10 percent extra you order 2 cubic yards of ready-mix, or buy 88 bags of 80 lb mix and mix it yourself.

A 12x12 slab suits a patio with a table for four, a larger shed or a workshop floor, and the square shape keeps the joint layout simple.

How much concrete for a 12x12 slab, by thickness

Volume is the area times the thickness in feet. The 12x12 slab covers 144 sq ft. Ordered volumes include 10 percent extra for uneven sub-base and spillage, the middle of the 4 to 10 percent NRMCA range, and ready-mix is sold in quarter yards.

BuildConcrete, netOrder with 10% extraTrucksWeight
4 in, plain1.78 cu yd (48 cu ft)2 cu yd1 (short load)7,392 lb
4 in, wire mesh1.78 cu yd (48 cu ft)2 cu yd1 (short load)7,392 lb
6 in, rebar2.67 cu yd (72 cu ft)3 cu yd1 (short load)11,088 lb

The weight uses 140 lb per cubic foot, Quikrete's figure for the mix. A 6 inch slab is half again the concrete of a 4 inch one for the same footprint, which is worth spending on where a car or a hot tub will sit and not on a walkway.

How many bags of concrete for a 12x12 slab

Bag counts come from the yields on the manufacturers' data sheets: an 80 lb bag makes 0.60 cu ft, 60 lb 0.45, 50 lb 0.375 and 40 lb 0.30. They include the 10 percent allowance.

Bag size4 in slab6 in slab
80 lb88 bags132 bags
60 lb118 bags176 bags
50 lb141 bags212 bags
40 lb176 bags264 bags

88 bags of 80 lb is about 3.5 tons of bagged mix. It is a big day with a mixer and two helpers, but it avoids a delivery minimum. Compare it against ready-mix, which for this order is a short load. The concrete bag calculator converts any bag size and brand.

12x12 slab cost, three builds

Installed prices at US averages: ready-mix $110 to $150 per cu yd, delivery, fuel and a short-load fee below a full truck, placing and finishing $2 to $3 per sq ft (HomeAdvisor, June 2026), wire mesh $0.83 to $0.98 per sq ft (homewyse, September 2026) and rebar $2 to $3 per sq ft (This Old House, March 2026).

BuildMaterials onlyInstalled rangeTypical per sq ftCrew days
4 in, plain$380 to $530$660 to $960 (typical $810)$61
4 in, wire mesh$490 to $670$780 to $1,100 (typical $940)$71
6 in, rebar$810 to $1,150$1,100 to $1,600 (typical $1,350)$91

A 2 cu yd order is well below the 8 to 12 yards a truck carries, so the estimate includes a short-load fee of about $100 ($80 to $120). Splitting a truck with a neighbor who is also pouring avoids it. The heavy build adds 18 bars of 20 ft No. 4 rebar in an 18 in grid, about 240 lb with laps and 10 percent spare; the rebar calculator lays out the grid.

Joints, thickness and permit

The 2024 IRC sets 3½ in as the minimum for a slab on ground (R506.1) over 4 in of granular base with a vapor retarder under floors. NRMCA advises control joints no farther apart than 24 times the thickness: 8 ft for a 4 in slab, 12 ft for a 6 in slab. On a 12x12 slab that means 1 joint each way at 4 in thick. Under IRC 2024 R105.2, sidewalks and driveways need no permit, and a free-standing patio slab is usually treated the same way. A slab that carries a building, such as a 12x12 garage or shed floor, is part of that building's permit.

Forming, placing and finishing is about 1 day for a two-person crew. Concrete reaches 2,500 psi at 7 days and 4,000 psi at 28 days (Quikrete data sheet), so keep vehicles off for the first week.

12x12 slab compared with other sizes

A 10x10 slab saves 0.54 cu yd less, $200 less installed. A 20x20 slab needs 3.16 cu yd more, $1,250 more installed.

Next steps for a 12x12 slab