How Much Concrete for a 10x10 Slab

Length × width × thickness ÷ 12: a 10x10 slab 4 in thick is 33.3 cu ft, 1.23 cu yd, so order 1.5 cu yd.

Units

Slab

Shape
Length
ft
in
Width
ft
in
in

Typical: walks 4 in (10 cm), patios 4 to 6 in (10 to 15 cm), driveways 4 to 8 in (10 to 20 cm).

%

NRMCA suggests ordering 4% to 10% over the plan volume for spillage, uneven ground and form bulge.

Yields from the Quikrete and Sakrete data sheets.

cu yd

NRMCA: mixer trucks carry 8 to 12 cu yd.

Price per
$

Optional. Your store's or supplier's price.

Enter every dimension above zero for each section. A post must be narrower than its hole, and a hole deeper than its gravel base.

A 10x10 slab poured 4 inches thick needs 1.23 cubic yards of concrete (33.3 cubic feet: 10 ft × 10 ft × 4 in ÷ 12). With 10 percent extra you order 1.5 cubic yards of ready-mix, or buy 62 bags of 80 lb mix and mix it yourself.

A 10x10 slab is a common size for a shed pad, an air conditioner base, a small patio or a hot tub pad, and it is small enough to pour and finish in one session.

How much concrete for a 10x10 slab, by thickness

Volume is the area times the thickness in feet. The 10x10 slab covers 100 sq ft. Ordered volumes include 10 percent extra for uneven sub-base and spillage, the middle of the 4 to 10 percent NRMCA range, and ready-mix is sold in quarter yards.

BuildConcrete, netOrder with 10% extraTrucksWeight
4 in, plain1.23 cu yd (33.3 cu ft)1.5 cu yd1 (short load)5,133 lb
4 in, wire mesh1.23 cu yd (33.3 cu ft)1.5 cu yd1 (short load)5,133 lb
6 in, rebar1.85 cu yd (50 cu ft)2.25 cu yd1 (short load)7,700 lb

The weight uses 140 lb per cubic foot, Quikrete's figure for the mix. A 6 inch slab is half again the concrete of a 4 inch one for the same footprint, which is worth spending on where a car or a hot tub will sit and not on a walkway.

How many bags of concrete for a 10x10 slab

Bag counts come from the yields on the manufacturers' data sheets: an 80 lb bag makes 0.60 cu ft, 60 lb 0.45, 50 lb 0.375 and 40 lb 0.30. They include the 10 percent allowance.

Bag size4 in slab6 in slab
80 lb62 bags92 bags
60 lb82 bags123 bags
50 lb98 bags147 bags
40 lb123 bags184 bags

62 bags of 80 lb is about 2.5 tons of bagged mix. It is a big day with a mixer and two helpers, but it avoids a delivery minimum. Compare it against ready-mix, which for this order is a short load. The concrete bag calculator converts any bag size and brand.

10x10 slab cost, three builds

Installed prices at US averages: ready-mix $110 to $150 per cu yd, delivery, fuel and a short-load fee below a full truck, placing and finishing $2 to $3 per sq ft (HomeAdvisor, June 2026), wire mesh $0.83 to $0.98 per sq ft (homewyse, September 2026) and rebar $2 to $3 per sq ft (This Old House, March 2026).

BuildMaterials onlyInstalled rangeTypical per sq ftCrew days
4 in, plain$300 to $420$500 to $720 (typical $610)$61
4 in, wire mesh$380 to $520$580 to $820 (typical $700)$71
6 in, rebar$610 to $880$810 to $1,200 (typical $1,000)$101

A 1.5 cu yd order is well below the 8 to 12 yards a truck carries, so the estimate includes a short-load fee of about $80 ($60 to $90). Splitting a truck with a neighbor who is also pouring avoids it. The heavy build adds 9 bars of 20 ft No. 4 rebar in an 18 in grid, about 120 lb with laps and 10 percent spare; the rebar calculator lays out the grid.

Joints, thickness and permit

The 2024 IRC sets 3½ in as the minimum for a slab on ground (R506.1) over 4 in of granular base with a vapor retarder under floors. NRMCA advises control joints no farther apart than 24 times the thickness: 8 ft for a 4 in slab, 12 ft for a 6 in slab. On a 10x10 slab that means 1 joint each way at 4 in thick. Under IRC 2024 R105.2, sidewalks and driveways need no permit, and a free-standing patio slab is usually treated the same way. A slab that carries a building, such as a 10x10 garage or shed floor, is part of that building's permit.

Forming, placing and finishing is about 1 day for a two-person crew. Concrete reaches 2,500 psi at 7 days and 4,000 psi at 28 days (Quikrete data sheet), so keep vehicles off for the first week.

10x10 slab compared with other sizes

A 12x12 slab needs 0.54 cu yd more, $200 more installed.

Next steps for a 10x10 slab