Stucco Calculator

Stucco bags = wall area × coat thickness ÷ 8.25 sq ft-inches per 80 lb bag: a 1,000 sq ft wall in 3-coat work takes 116 bags with 10% extra, 50 for each base coat and 16 for the finish.

Units
Wall size
Wall length (all walls)
ft
in

Add the lengths of every wall you will stucco.

Wall height
ft
in
sq ft

Total area to leave out. A door is about 20 sq ft, a window about 15.

Stucco system

ASTM C926 Table 4 sets the coat thicknesses by the wall type.

%

Rebound, droppings and mix left in the bucket. 10% is a working allowance; the data sheets warn coverage varies with the wall.

Labor and material prices are scaled to typical levels in your state.

Bags of stucco mix, 80 lb, all coats, with 10% extra

116bags

1,000 sq ft of wall, ⅞ in thick in all. The data sheet coverage range gives 108 to 126 bags.

Bags per coat

CoatThicknessSq ft per bagBags
Scratch coat⅜ in2250
Brown coat⅜ in2250
Finish coat⅛ in7016
Lath sheets
69sheets
Mixing water
170gal
Dry mix
9,280lb
Control joint panels
7at most 144 sq ft
Total thickness
⅞in
Cost per sq ft
$8.01typical
WallScratchBrownFinish⅞ inLath dashed

Thickness check

  • Three-coat over lath ⅞ in

    ⅞ in nominal, ASTM C926 Table 4

Installed cost range for this wall

$8,000

Low $6,400High $9,700
ItemMaterialsLaborTotal

Three-coat cement stucco

1,000 sq ft, lath, coats and finish

$2,800$5,200

$8,000

$6,400 to $9,700

Prices are US averages scaled to your state, updated September 2026.

The math
  1. Net wall area

    120 ft × 9 ft − 80 sq ft openings = 1,000 sq ft

  2. Scratch coat

    1,000 sq ft × 1.1 ÷ (8.25 sq ft-in ÷ ⅜ in = 22 sq ft per bag), rounded up = 50 bags

  3. Brown coat

    1,000 sq ft × 1.1 ÷ (8.25 sq ft-in ÷ ⅜ in = 22 sq ft per bag), rounded up = 50 bags

  4. Finish coat

    1,000 sq ft × 1.1 ÷ (8.75 sq ft-in ÷ ⅛ in = 70 sq ft per bag), rounded up = 16 bags

  5. Total bags

    50 + 50 + 16 = 116 bags

Coverage per bag = 8.25 sq ft-inches (Quikrete's 20 to 24 sq ft at 3/8 in, 15 to 18 at 1/2 in, 10 to 12 at 3/4 in) ÷ thickness. Finish coat: 70 sq ft at 1/8 in.

Material list

1,000 sq ft wall, 3-coat stucco

QuantityItem
50bags

Scratch and brown base coat stucco, 80 lb

scratch coat at ⅜ in

50bags

Scratch and brown base coat stucco, 80 lb

brown coat at ⅜ in

16bags

Finish coat stucco, 80 lb

finish coat at ⅛ in

69sheets

Metal lath or woven wire, corrosion resistant

16 sq ft each after laps

Stucco bags = wall area × coat thickness ÷ 8.25 sq ft-inches per 80 lb bag, coat by coat. A 1,000 sq ft wall in classic 3-coat stucco over lath takes 116 bags with 10% extra: 50 for the scratch coat, 50 for the brown coat and 16 for the finish coat, plus 69 sheets of lath. The same wall in a 1-coat system at ⅜ in with a finish coat takes 66 bags. Pick the system, the wall behind it and the state, and the calculator gives bags per coat, lath, water and an installed cost range.

How the stucco is calculated

Quikrete's base coat data sheet gives coverage for an 80 lb bag at three thicknesses: 20 to 24 sq ft at ⅜ in, 15 to 18 sq ft at ½ in and 10 to 12 sq ft at ¾ in. All three rows are the same 7.5 to 9 sq ft-inches a bag, so coverage is that figure divided by the thickness. The calculator takes the middle, 8.25, for the base coats, and the finish coat sheet's 70 sq ft at ⅛ in (8.75) for the finish.

Bags per coat = wall area × (1 + waste) ÷ (8.25 ÷ coat thickness in inches), rounded up

Worked example: 1,000 sq ft, 10% extra. A ⅜ in coat covers 8.25 ÷ 0.375 = 22 sq ft a bag, so 1,000 × 1.1 ÷ 22 = 50 bags each for the scratch and brown coats. The ⅛ in finish covers 70 sq ft a bag: 1,100 ÷ 70 = 15.7, so 16 bags. Lath at 16 sq ft a sheet after laps is 69 sheets. Mixing takes 5½ quarts a base bag and 2 gallons a finish bag: 170 gallons in all. The coverage ranges in the data sheet give 108 to 126 bags, so the calculator shows that band too.

3-coat stucco: bags per coat

ASTM C926 Table 4 sets the nominal thickness of each coat by the wall behind it (vertical work):

Wall behindSystemCoatsTotalBags per 1,000 sq ft, 10% extra
Wood or steel frame with lath3-coat⅜, ⅜, ⅛ in⅞ in50, 50, 16 = 116
Concrete block or brick3-coat¼, ¼, ⅛ in⅝ in34, 34, 16 = 84
Concrete block or brick2-coat⅜, ⅛ in½ in50, 16 = 66
Poured concrete2-coat¼, ⅛ in⅜ in34, 16 = 50

The IRC (R703.7.2) requires three coats over metal or wire lath and allows two over masonry or concrete. ASTM C926 adds that two-coat work is only for solid bases, so the calculator refuses 2-coat on a framed wall.

1-coat stucco

One-coat fiberglass reinforced stucco goes on in a single pass over lath and building paper, then gets a color or texture coat. Quikrete's One Coat data sheet has the same coverage table as its base coat, calls for at least ⅜ in over lath and wants control joints so no panel is over 144 sq ft. It also says only experienced or manufacturer-certified installers should apply it.

Lath, paper and trim

Over a frame wall the IRC calls for corrosion-resistant lath fastened with 1½ in 11-gage nails or ⅞ in 16-gage staples at 7 in or closer, two layers of Grade D paper in dry climates, and a weep screed at least 4 in above the ground with a 3½ in flange. The calculator counts lath sheets only for the frame wall, at 16 sq ft each (Donley Brick's figure for a sheet of wire mesh after laps). Add corner bead, screed and paper from your wall plan.

How long between coats

The IRC says the second coat of a three-coat job goes on no sooner than 48 hours after the first, and the finish coat not until 7 days after the second. In a two-coat job the finish waits 7 days after the base. Quikrete's data sheets add: mist-cure the base coat once it has set and do not apply below 40°F or above 100°F without cold or hot weather precautions.

Stucco cost per square foot

This Old House, quoting Homewyse (updated April 2026), puts traditional cement stucco at $6.36 to $9.66 a sq ft installed and one-coat systems at $3 to $9.75. HomeAdvisor (June 2026) gives $7 to $9 and says labor is 50 to 80% of the bill. The calculator applies those rates, splits them 65% labor and 35% materials, and scales them by your state, so 1,000 sq ft of 3-coat runs about $6,400 to $9,700 at US average prices. The "do it yourself" switch drops the labor share.

Mixing your own stucco

Quikrete's portland cement data sheet lists two ASTM C926 scratch and brown coat recipes by volume: 1 part cement, ½ part Type S lime and 4½ to 6 parts plaster sand, or 1 part cement, 1 part Type N masonry cement and 6 to 8 parts plaster sand. The bagged mix above saves you weighing sand.

Next: the rest of the wall

Blocks behind stucco need mortar, and a stone wainscot or accent wall on the same house is sized in the stone veneer calculator. Compare with siding, and see the brick calculator for masonry walls. For interior walls, plaster is the matching tool. Every block, brick and concrete tool is in the concrete and masonry calculators.