Concrete Footing Calculator

Add the footings, pads and foundation walls of the job and get yards, bags and trucks, with an IRC check on footing size and depth.

Units

Footing

Shape
Total footing length
ft
in

Add up every run, e.g. the perimeter of the house.

in

IRC R403.1.1: at least 12 in wide.

in

Foundation wall

Shape
Wall length
ft
in
Wall height
ft
in
in
%

NRMCA suggests ordering 4% to 10% over the plan volume for spillage, uneven ground and form bulge.

Yields from the Quikrete and Sakrete data sheets.

cu yd

NRMCA: mixer trucks carry 8 to 12 cu yd.

Price per
$

Optional. Your store's or supplier's price.

in

IRC R403.1.4: at least 12 in, and below your local frost depth.

Enter every dimension above zero for each section. A post must be narrower than its hole, and a hole deeper than its gravel base.

A continuous footing 16 inches wide and 8 inches thick holds 0.89 cubic feet of concrete per running foot, so 120 feet of it, the perimeter of a 30 × 30 ft building, takes 106.7 cubic feet or 3.95 cubic yards. Put a 4 ft foundation wall 8 inches thick on top and the job grows to 426.7 cubic feet: 17.5 cubic yards to order with a 10% allowance, two mixer trucks.

How footing and foundation concrete is calculated

Every footing and wall is a long box. Multiply the total run by the cross-section:

Cubic feet = total length (ft) × width (in) ÷ 12 × thickness (in) ÷ 12

A foundation wall is the same with its height and thickness: length × height (ft) × thickness (in) ÷ 12. Square pads under piers or posts are length × width × thickness, times how many there are. The calculator adds every section into one order and draws the cross-section of the one you are editing.

For the example:

  • Footing: 120 × 16 ÷ 12 × 8 ÷ 12 = 106.67 cu ft
  • Wall: 120 × 4 × 8 ÷ 12 = 320 cu ft
  • Total 426.67 cu ft, 15.80 cu yd; with 10% extra 17.38 cu yd, ordered as 17.5

At 10 cubic yards per truck that is one full truck and a second carrying 7.5 yards.

Measuring the footing length

Add up every run. For a rectangular building, the centerline perimeter is close enough: 2 × (length + width). Count interior footings under bearing walls separately, and add each run once, so corners are not counted twice. A footing that steps down a slope is still the sum of its lengths; add the extra concrete in the risers as short wall sections if they are formed.

IRC minimum footing size and depth

The 2024 International Residential Code sets the floor for footings; the calculator checks your entries against it:

RuleMinimumSection
Footing width12 inR403.1.1
Footing thickness6 inR403.1.1
Projection past the wall2 in, and not more than the footing thicknessR403.1.1
Depth below undisturbed ground12 inR403.1.4
Rebar cover where cast against earth3 inR403.1.3

These are minimums, not a design. The width actually required depends on the soil and the load (IRC Table R403.1), and the bottom must sit below the local frost line, which your building department publishes. The calculator's depth check only tests the 12 inch minimum.

Concrete footing calculator with footings and a slab

A "slab with footings" can mean two things. If the slab and its edge are poured together, pick "Slab with footings" and turn on the thickened edge: the calculator adds the deeper band around the perimeter. If the footings are poured first and the slab later, enter the footing, then add the slab as its own section to see the whole job; order each pour separately, since each will need its own truck. The concrete slab calculator adds an installed price for the slab.

Footing pads

Pads under posts and piers default to 24 × 24 inches and 12 inches thick, 4 cubic feet each. Eight of them with 10% extra need 35.2 cubic feet, 59 bags of 80 lb mix. For round piers poured in a form tube, the sonotube concrete calculator does the cylinder math and subtracts the post; for deck piers specifically, see the deck footing calculator.

Concrete per 10 feet of footing

FootingPer 10 ftPer 100 ft
12 × 6 in (IRC minimum)5 cu ft1.85 cu yd
16 × 8 in8.9 cu ft3.29 cu yd
20 × 10 in13.9 cu ft5.14 cu yd
24 × 12 in20 cu ft7.41 cu yd

Plan volumes, before waste. Footings are dug into soil rather than formed, so trenches run wide; a larger allowance than 10% is common in loose ground.

Next steps

Size the rebar for the footing: the IRC's seismic provisions call for a No. 4 bar near the bottom, and the rebar calculator handles laps and bar counts. Turn the total into a truck order with the concrete yard calculator, price it in the concrete cost calculator, or build the wall in block instead with the cinder block calculator. The concrete calculator takes every other shape.